WHAT IS SHASSIC ?
Safety and Health Assessment System in Construction or SHASSIC is an independent method to assess and evaluate the safety and health performance of a contractor in construction works/ projects. SHASSIC was developed by a Technical Committee comprises of industry stakeholders. It was published as Construction Industry Standard or CIS 10 : 2008 in November 2008.
SHASSIC OBJECTIVES
SHASSIC was designed and developed to enable the user to achieve any or combination of the following objectives:
USE OF SHASSIC IN CONSTRUCTION ACTIVITIES
SHASSIC is intended to complement the normal contractual requirement and specification in a project. It is not intended to be used independently as working requirement and specification. Unless specified in the project contract, safety and health designated person should not use SHASSIC to decide if the project site or parts of the project site are in accordance with requirement of the relevant Acts and Regulations or OSH Management System. It is still the responsibility of the contractor to ensure that safety and health of the construction site conforms to legislations requirement, approved standards, code of practice, guidelines, specifications and contractual requirements.
SHASSIC is intended to complement the normal contractual requirement and specification in a project. It is not intended to be used independently as working requirement and specification. Unless specified in the project contract, safety and health designated person should not use SHASSIC to decide if the project site or parts of the project site are in accordance with requirement of the relevant Acts and Regulations or OSH Management System. It is still the responsibility of the contractor to ensure that safety and health of the construction site conforms to legislations requirement, approved standards, code of practice, guidelines, specifications and contractual requirements.
Preferably, the assessment shall be carried out when there are different type of activities that are on going at same time (concurrent activities) and many workers of different trades are involved at the site. It is recommended that SHASSIC assessment be carried out when the actual physical work progress had achieved or fall within 25 % to 75 %.
SCOPE OF SHASSIC
SHASSIC sets out the safety and health management and practices of contractor for various aspects of the construction work activities. SHASSIC cover 3 (three) main components of assessment such as document check, site/ workplace inspection and employees interview and covering components such as OSH policy, OSH organization, HIRARC, OSH training and promotion, machinery and equipment management, materials management, emergency preparedness, accident investigation and reporting and records management and performance monitoring.
Application shall cover COSH management system and practices during construction work activities, particularly work activities covered under Occupational Safety and Health Act, 1994, Factories and Machinery Act, 1967 and regulations made under this act such as Factories and Machinery (Building Operations and Works of Engineering Construction) (Safety) Regulations 1986, and Factories and Machinery (Safety, Health and Welfare) Regulations, 1970.
Application shall cover COSH management system and practices during construction work activities, particularly work activities covered under Occupational Safety and Health Act, 1994, Factories and Machinery Act, 1967 and regulations made under this act such as Factories and Machinery (Building Operations and Works of Engineering Construction) (Safety) Regulations 1986, and Factories and Machinery (Safety, Health and Welfare) Regulations, 1970.
For the purpose of terms and references, the following Acts, Regulations and OHS management system standards shall take precedence, Occupational Safety and Health Act, 1994 (Act 514) and Regulations, Factories and Machinery Act, 1967 (Act 139) and Regulations and Rules, OHSAS 18001: 2007, MS 1722: 2005 and ILO OHS MS: 2001.
SHASSIC ASSESSMENT
Basically, SHASSIC assessment is divided into 3 (three) different components namely, document check; work site inspection and employee interview.
Document check
Checking of OSH related documents and records will enable the assessor to determine the compliances of the establishment of safety and health programmes and activities. There are 63 questionnaires identified for this component check and is listed out in Annex A.
Checking of OSH related documents and records will enable the assessor to determine the compliances of the establishment of safety and health programmes and activities. There are 63 questionnaires identified for this component check and is listed out in Annex A.
Site/ workplace inspection
There are 62 items identified for inspection for this component and they are listed out in Annex B. Workplace inspection shall be carried out at 5 (five) highly risk areas within a site. These locations will be determined by the SHASSIC assessor. The assessor may also discuss with the principal contractor prior to selection of these high risk areas for assessment.
This assessment shall provide the assessor with the valuable visual comparison evidence on the OSH programs implemented, enforced and practiced at site/ workplace.
There are 62 items identified for inspection for this component and they are listed out in Annex B. Workplace inspection shall be carried out at 5 (five) highly risk areas within a site. These locations will be determined by the SHASSIC assessor. The assessor may also discuss with the principal contractor prior to selection of these high risk areas for assessment.
This assessment shall provide the assessor with the valuable visual comparison evidence on the OSH programs implemented, enforced and practiced at site/ workplace.
Employees interview
Employees shall be randomly selected from all levels and occupation so that they could be interviewed by the assessor using established standard questionnaire. There are 48 questions for this component as listed in Annex C.
The employees in this component are categorised into 3 (three) categories, as spelt out in Annex C. The numbers of employee from each category to be interviewed are as follows:
Employees shall be randomly selected from all levels and occupation so that they could be interviewed by the assessor using established standard questionnaire. There are 48 questions for this component as listed in Annex C.
The employees in this component are categorised into 3 (three) categories, as spelt out in Annex C. The numbers of employee from each category to be interviewed are as follows:
WEIGHTAGE & SCORE
The weightage for safety and health performance are allocated in accordance to 3 (three) components as shown in Table 1 and the score calculation is shown below.
WHO CAN BE A SHASSIC ASSESSOR ?
SHASSIC Assessor must be a person who is qualified and have certain years of working experience in construction industry. A SHASSIC Assessor shall fulfil one of the following criteria below.
* Note : CSHO means a person who is registered with DOSH as Safety & Health Officer and attended successfully 5 (five) days course organised by CIDB for Construction Safety & Health Officer.
Contractors may engage any qualified person above to carry out SHASSIC assessment or alternatively they can make arrangement with CIDB to carry out SHASSIC assessment. Currently CIDB is providing this service Free of Charge ( FOC ) and contractors are entitled for 20 CCD for a successful assessment.
Contractors just need to fill in a FORM which is available at Standard & Quality Division, 10th Floor, Grand Seasons Avenue, Jalan Pahang, 53000 Kuala Lumpur and fax to 03 - 40451808. That's all, so simple ! CIDB officers will contact the contractor and will make arrangement for SHASSIC assessment.
Contractors just need to fill in a FORM which is available at Standard & Quality Division, 10th Floor, Grand Seasons Avenue, Jalan Pahang, 53000 Kuala Lumpur and fax to 03 - 40451808. That's all, so simple ! CIDB officers will contact the contractor and will make arrangement for SHASSIC assessment.
HOW CONTRACTORS CAN BENEFIT FROM SHASSIC ASSESSMENT ?
Some of the benefits that the contractor could expect after carrying out SHASSIC assessment are as listed below :-
CONCLUSION
SHASSIC was developed to assist everyone particularly the contractors in managing their safety and health at construction sites based on safety and health performance's assessment. CIDB believes, by using SHASSIC assessment system as a norm of practice at site, accidents could be prevented or minimized.
Course Brochure (click to view)
2 comments:
Ergonomic assessment is the process of designing the workplace conditions and various job demands according to the working population. Ergonomic assessment keeps in mind the capabilities and in capabilities of the employees. Ergonomic training can be beneficial in many ways some of the advantages are as follows:
I want to share with you all here on how I get my loan from Mr Benjamin who help me with loan of 400,000.00 Euro to improve my business, It was easy and swift when i apply for the loan when things was getting rough with my business Mr Benjamin grant me loan without delay. here is Mr Benjamin email/whatsapp contact: +1 989-394-3740, lfdsloans@outlook.com
Post a Comment